    #HeadsUp: Riverton Main Street concrete repair public meeting planned February 23rd

    This #headsup is brought to you by Bailey’s Tire and Auto Service.

    (Riverton, WY) – Citizens and business owners are invited to a Tuesday, February 23rd, public meeting regarding this spring’s $1.443 million concrete rehabilitation project in downtown Riverton, according to a WYDOT press release.

    The 6:00 pm February 23rd public meeting will be held at Riverton City Hall. Attendees will be socially distanced, and masks are required. The meeting can also be watched online via the City of Riverton’s YouTube Channel.

    Written public comments are due by Tuesday, March 9th, 2021, and may be emailed by [email protected] or mailed to WYDOT, PO Box 1784, Riverton, WY 82501.  

    The concrete rehabilitation project on Riverton’s Main Street is 0.50 miles in length between North Federal Boulevard and North 1st Street. The project includes concrete milling, asphalt paving, and curb, gutter and Americans with Disabilities Act ramp repairs.
    Prime contractor on the project is 71 Construction of Riverton. By contract, all curb, gutter and ADA improvements must be completed by the contractor prior to street milling and paving operations.

    The project is scheduled to begin in early April.

    By contract, project work is required to be phased so that 2-way traffic is maintained on half of the roadway at all times. Intersection closures are planned on half of Main Street during this quick-moving project.

    Project completion date is Oct. 31, 2021.

    Project questions may be directed to WYDOT Resident Engineer Robert Scheidemantel, P.E., at (307) 856-1341, or by email at [email protected].