June 20-30: Interior Demo & Prep Work
June 26- July 30: Abatement Removal, Installation of temporary and permanent fencing, Exterior Demo- stadium seating area, Sidewalk removal, and Access Road installation for demolition.
Aug 1st – Oct 1st: TAC Building Demolition & Material Processing (concrete & brick crushing)
Oct 1st – Nov. 30th: Site Reclamation, grading, dirt work, final fencing.